Project Spotlight: 710 Freeway

I-710 Project Update - Phase 4 Completed 3 Weeks Early

Sully-Miller Contracting Co. has completed the work for seven 55 hour weekends on the I-710.  The work was originally planned to take 10 55-hour weekends. But we were able to complete all work on both the Southbound and Northbound lanes a full three weeks early.
The first 4 weekends consisted of removal of existing concrete, asphalt, base material and subgrade, grading, placing base materials, hot mixed asphalt from Blue Diamond Materials and concrete on the Southbound Lanes. The Southbound lanes were then paved with rubberized hot mixed asphalt. 

Underground crossing on the Northbound 710Underground crossing on the Northbound 710 Starting on the 5th weekend Sully-Miller Contracting Co.'s crews started working on the Northbound lanes, consisted of removal of existing concrete, asphalt, base material and subgrade, grading, placing base materials, hot mixed asphalt from Blue Diamond Materials and concrete. Traffic was diverted to the Southbound lanes as to have minimal impact on local traffic. The 7th weekend the Northbound lanes were paved with rubberized hot mixed asphalt.
On all 7 weekends the freeway was open earlier than scheduled for the Monday morning commute.

Sully-Miller Contracting Co. is now moving in to Phase 5, which will complete the reminder of the work during the normal working hours.

Weekend Work 

Movable BarrierMovable Barrier Grade crew setting out to workGrade crew setting out to work
Undergound crew working under the Imperial Highway overpassUndergound crew working under the Imperial Highway overpass Truck Traffic Jam on the Northbound 710Truck Traffic Jam on the Northbound 710
Removals at the Firestone Blvd exitRemovals at the Firestone Blvd exit Existing Pavement Removed from the Northbound Freeway lanesExisting Pavement Removed from the Northbound Freeway lanes
Grading the northbound lanes in the wee hours of the morningGrading the northbound lanes in the wee hours of the morning

Excavator removing subgradeExcavator removing subgrade

Excavators removing existing 710 freewayExcavators removing existing 710 freeway Concrete Crew drilling dowels in bridge with skiploader gradingConcrete Crew drilling dowels in bridge with skiploader grading
Grading in the early morning hours on the Northbound 710 FreewayGrading in the early morning hours on the Northbound 710 Freeway Movable barrier on Southbound 710 FreewayMovable barrier on Southbound 710 Freeway

Weekend Work 
  

Profilographing Southbound 710 Freeway Rubber CapProfilographing Southbound Lanes Rubber Cap Breaking Out Inlets on the 710 FreewayUndergound Crews Breaking Out Inlets
Breaking out inlets on the southbound lanesBreaking Out Inlets Underground crews breaking out inlets on the southbound laneBreaking Out Inlets
Grading southbound I-710 Freeway LanesBlade Grading Southbound Lanes Grading on the I-710 Weekend #1Grading the Southbound Lanes
Night Time paving on the I-710Night Time Paving Paving Southbound I-710 at NightPaving Crew at Night
Pulling Forms from Concrete Slab in Southbound Lanes of I-710Pulling Forms from Concrete Slab Slot Paving and Drilling Dowels at nightSlot Paving and Drilling Dowels
Drilling Dowels into the Existing Concrete on I-710Drilling Dowels into the Existing Concrete Concrete crew drilling dowels at night on Weekend #1 of the I-710 projectConcrete Crew Drilling Dowels

 

Sully-Miller Contracting Co. broke ground on the 710 Freeway SR710 project in July of 2009.

This project is a critical improvement to the Alameda Corridor, stretching from the 105 Freeway north to Firestone Blvd.  This 2-year project also crosses the Los Angeles River. Scheduled to have a minimal impact on traffic, our crews will be working both days and nights, and ten consecutive 55 hour weekends.

The work includes removal of concrete pavements, and the installation of new center medians, guard rails, retaining walls, overhead signs and asphalt pavement. Blue Diamond Materials will be supplying the asphalt materials with aggregates from United Rock Products.

Overseeing the work is Project Manager Travis Clausen, Project Superintendent Arnulfo Aguirre, Project Engineer Mauricio Arreola, and Project Foreman Juan Lizama.

710 Freeway at Rush Hour

 

 


For more information about this project visit the Caltrans website.

You can also view the LA Times article about this project titled 'A Smooth Idea for the 710 Freeway'. (Published September 30, 2009)

Work on Slopes and Walls

Pumping Concrete for Retaining Wall Foundation at Night on 710 FreewayPumping Concrete for Retaining Wall Foundation Night Pour of PCC for Retaining Wall FoundationsNight Pour
Caltrans 710 Freeway Slope with Rebar Set for Retaining WallRebar Set for Retaining Walls Caltrans 710 Freeway Grading Slopes at NightGrading Slope
Caltrans 710 Freeway Footings for WallsSurvey Caltrans 710 Freeway Digging Footings for WallsDigging Footings
Caltrans 710 Freeway Excavation and SlopesExcavation  

Median & Center Lanes Work

Forming Center Barrier on 710 FreewayForming Center Barrier Moving Barrier on 710 FreewayMoving the Barrier
Caltrans 710 Freeway Night PavingNight Paving Caltrans 710 Freeway Slurry over Center UnderdrainSlurry over the Underdrain
Caltrans 710 Freeway Underdrain in Center MedianUnderdrain Caltrans 710 Freeway CenterCenter Freeway
   

Project Gallery Environment Request A Quote Quality Safety People